A509 / M1 Junction 14 Project - Efficiencies in Work Practices

MK Highways undertook a 9 day nighttime closure of Junction 14 of the M1 to resurface the A509, see how we combined multiple work to create efficiencies

Due to the nature and difficulties of the location work had to take place overnight and Traffic Management costs for a single scheme were high therefore discussions through Early Contractor Involvement (ECI) took place with Ringway with a view to co-ordinate as much ancilliary work to eliminate the need to revisit this site for any future maintenance.

In addition in order to maximise the lifecycle of the road surface at a location that has high volumes of traffic MK Highways specified a 35/14 HRA with a 20mm Pre Coated Chipping in line with the authorities strategy for the networks grid road roundabouts to enhance longevity of the road surface.

The scheme also allowed access to enable the 12 m street lighting columns to be converted to LED technology again in line with its Asset Strategy to reduce energy and maintenance costs and enhance the lighting stocks lifecycle.

Facts and Figures:

Work carried out over 9 Night Shifts

2480 man hours of work

Liaison with Highways England to shut the Motorway Junction

10,222 square metres of surfacing laid (1228 tonnes of asphalt) over 1,000 square metres per night

1228 tonnes of road planing's recycled into general construction

47 No. 12 metre columns converted to LED lanterns

1 No. high definition electronic VMS installed

1,400 linear metres of white lining installed

96 linear metres of bridge joints upgraded

126 linear metres of traffic ducts and loops upgraded

45 linear metres of vehicle safety barrier upgraded

Repaired 5 No. static signs. 40 linear metres of kerbing renewed

68 No. Gullies inspected and cleaned

75 No. road signs, 250 no. road cones and 125 l/m barriers erected every night before works can start

Benefits

£39,000 saving in Traffic Management

7 days reduction in road closures

Enhanced road surface lifecycle

Energy, maintenance and carbon reduction on Street Lighting

Upgraded traffic loops to reduce congestion

 

Latest news

MK Highways recovers over £400,000 in damage costs to highway assets

MK Highways has taken a pro-active step towards recovering damage to our assets caused by drivers on our roads.

more
MK Highways Awarded £2.271 million

Milton Keynes has been awarded £2.271 m grant by the Department for Transport who has identified that the funding should be directed towards repairing damaged roads, tackling potholes and repairs to bridges/structures.

more

To ensure we give you the best experience on our website we use Cookies. You can change your cookie settings at any time. However, if you continue without changing your settings we will presume you are happy to receive all cookies on the Milton Keynes Highways website.

Continue